Service Facilities

Connected Facilities and Capacity Management

Service Facilities and rail related services are a broad yet crucial category of railway infrastructure. With each train path and train movement, there is always an associated need for one or multiple types of service facilities. This can include a slot at a station, a track to park the train, access to a freight terminal for loading or unloading goods, service at a maintenance facility, and more. Without access to such facilities, a train cannot operate or serve fully its purpose, thus making service facilities and their access just as important as the railroad tracks and paths that connect them. With the variety of types of rail connected facilities, there is also a wide variance in ownership, which can be owned and maintained by infrastructure managers, independent companies, or even railway undertakings themselves. FTE and its members highlight the importance of rail connected facilities as an essential element of improving the competitiveness of railways and the international operation.

There are numerous types of Service Facilities, each with its own relevance for passenger and/or freight undertakings. Below are listed some of the most important service facilities as defined by the European Union in the Single European Railway Area directive (SERA – 34/2012):

 

Service facilities pose many challenges from the perspective of capacity management and timetabling. Many of these challenges have thus far not been sufficiently tackled by the railway sector, with most of the consequences of inaction falling on railway undertakings. Firstly, the involvement of service facility owners and railway undertakings´ needs into the infrastructure development is limited and not internationally aligned. Secondly, current processes for the allocation of capacity do not sufficiently include the associated space/services/slots that are needed at the relevant service facility. This means that railway undertakings must often independently contract with the relevant facilities, with no guarantee that their availability will match the train paths that they have been allocated. The fragmentation of rail connected facilities and different processes and access conditions makes harmonization with path allocation difficult and cumbersome, moreover, this can lead to facilities which are not adequately equipped to manage the demands of the market. There are many situations where problems can arise, for example:

Processes for planning capacity restrictions for maintenance works often do not consider the effect on access to rail connected facilities.

Storage sidings are often removed to save money, meaning less trains can be stored, and ultimately meaning less trains can be run than otherwise could be.

Railway undertakings (RUs) are dependent on infrastructure managers and their processes for capacity allocation and timetabling. When these processes do not sufficiently integrate service facilities and this negatively effects the running of the train, the loss is ultimately borne by the RU. For RUs this means delays, cancelled trains, irregular service, loss of profits, higher administrative burden, and in the end the lower competitiveness of rail compared to trucks and buses for freight and passengers. With the development of new and harmonized processes for timetabling and capacity management comes opportunities for the integration of service facilities into such processes. This can increase efficiency and improve the business outlook for RUs.

FTE work on this topic

Members of FTE, of which more of them are also Service Facility Operators (SFOs), underline the need to improve the alignment of processes for facilities and rail planning and capacity allocation. This need was also mentioned by numerous stakeholders during the consultation process for the initiative of the European Commission “International freight and passenger transport – increasing the share of rail traffic”. The closer alignment of service facilities is now stated as the requirement in the soon expected EU Regulation “on the use of railway infrastructure capacity in the single European railway area”. After the Regulation enters in force, the sector has to come up with the process and IT standards for whole Europe, and this is where FTE and its members are preparing a solid ground with the research for the future discussions between market stakeholders (RUs, Infrastructure Managers, Regulatory Bodies and 3rd party Service Facility Operators)

FTE office continuously cooperates on with university students and trainees, who are supporting the FTE with data collection and suggestions. FTE has established a Task Force on Service Facilities in order to provide aggregated input to European Fora and discuss information recognized by the research.  

Overview of activities:

  • January 2023: the research has started in January 2023 with the focus on Storage Sidings and Freight Terminals.
  • May 2023: the preliminary results presented by Giuseppe Miccoli and discussed in the FTE Working Groups Freight and Passenger.
  • April 2024: the first version of the report on storage sidings published.
  • December 2024: the first version of the report on freight terminals published.
  • Expected in 2025: publication of the first report on passenger stations and update of the report on storage sidings.
  • December 2024: the first version of the report on freight terminals published.
  • During 2025: 
    • Establishment of Task Force Service Facilities,
    • Research conduction on Passenger Stations,
    • preliminary results on Passenger Stations presented by Radovan Tegdes in the FTE Working Groups Freight and Passenger.
  • Upcoming 2026: 
    • Summer: First version of Passenger Station report to be published
    • Research starts on Marshalling Yards 
    • Participation and input provision in SERAF Sub-group on Service Facilities

Presentation of Preliminary Results (Sidings, Terminals) WG Freight/Passenger May 2023 (PDF)
Storage Sidings Report v0.5 April 2024  (PDF)
Freight Terminal Report v0.3 December 2024 (PDF)

Presentation of Preliminary Results (Passenger Stations) - WG Freight/Passenger September 2025 (PDF)